Encyclopedia > Earned Value Management

Earned Value Management (commonly abbreviated and referred to just as EVM) is a project management technique that seeks to measure forward progress in an objective manner. EVM is touted as having a unique ability to combine measurements of technical performance (i.e., accomplishment of planned work), schedule performance (i.e., behind/ahead of schedule), and cost performance (i.e., under/over budget) within a single integrated methodology. Proponents also claim that it provides an early warning of performance problems. Additionally, EVM promises to improve the definition of project scope, prevent scope creep, communicate objective progress to stakeholders, and keep the project team focused on achieving progress. Image File history File links Broom_icon. ... Image File history File links Broom_icon. ... Project Management is the discipline of organizing and managing resources (e. ... Scope (products) of a project is the sum total of all projects products and their requirements or features. ... It has been suggested that this article or section be merged into Mission creep. ... A corporate stakeholder is a party who affects, or can be affected by, the companys actions. ... A project team is a team used for grouping people based on a common function. ...


EVM emerged as a financial analysis specialty in United States Government programs in the 1960s, but it has since become a significant branch of project management and cost engineering. Project management research investigating the contribution of EVM to project success suggests a moderately strong positive relationship [1]. Implementations of EVM can be scaled to fit projects of all sizes and complexity. Financial analysis refers to an assessment of the viability, stability and profitability of a business, sub-business or project. ... The government of the United States, established by the United States Constitution, is a federal republic of 50 states, a few territories and some protectorates. ... The 1960s decade refers to the years from 1960 to 1969. ... Project Management is the discipline of organizing and managing resources (e. ... Per AACE International (Association for the Advancement of Cost Engineering), Cost Engineering is the area of engineering practice where engineering judgment and experience are used in the application of scientific principles and techniques to problems of cost estimating, cost control, business planning and management science, profitability analysis, project management, and... This article is about the concept. ...

Contents

Introduction to EVM

Essential features of any EVM implementation include (1) a project plan that identifies work to be accomplished, (2) a valuation of planned work, called planned value (PV), and (3) pre-defined “earning rules” (also called metrics) to quantify the accomplishment of work, called Earned Value (EV). EVM implementations for large or complex projects include many more features, such as indicators and forecasts of cost performance (over/under budget) and schedule performance (behind/ahead of schedule). The most basic requirement of an EVM system, however, is that it quantifies progress using PV and EV. (As defined in the Project Management Body of Knowledge (PMBOK) 2000 Edition): A project plan is A formal, approved document used to guide both project execution and project control. ...


Project Tracking without EVM

It is helpful to see an example of project tracking that does not include earned value performance management. Consider a project that has been planned in detail, including a time-phased spend plan for all elements of work. Figure 1 shows the cumulative budget for this project as a function of time (the blue line, labeled PV). It also shows the cumulative actual cost of the project (red line) through week 8. To those unfamiliar with EVM, it might appear that this project was over budget through week 4 and then under budget from week 6 through week 8. However, what is missing from this chart is any understanding of how much work has been accomplished during the project. If the project was actually completed at week 8, then the project would actually be well under budget and well ahead of schedule. If, on the other hand, the project is only 10% complete at week 8, the project is significantly over budget and behind schedule. A method is needed to measure technical performance objectively and quantitatively, and that is what EVM accomplishes. Image File history File links EVM_Fig1. ... Image File history File links EVM_Fig2. ... Image File history File links EVM_Fig3. ... Image File history File links EVM_Fig4. ...

Project Tracking with EVM

Consider the same project, except this time the project plan includes pre-defined methods of quantifying the accomplishment of work. At the end of each week, the project manager identifies every detailed element of work that has been completed, and sums the PV for each of these completed elements. Earned value is also commonly calculated as Percent Complete times Budget at Completion (BAC), This accumulation is called "earned value" (EV), and it can be computed monthly, weekly, or as progress is made. A project manager is the person who has the overall responsibility for the successful planning and execution of any project. ...

Earned Value (EV)

 begin{align} EV & = %Complete * BAC  & or EV & = sum_{Beginning}^{Current} PV_{Work Elements Completed} end{align}


Figure 2 shows the EV curve (in green) along with the PV curve from Figure 1. The chart indicates that technical performance (i.e., progress) started more rapidly than planned, but slowed significantly and fell behind schedule at week 7 and 8. This chart illustrates the schedule performance aspect of EVM. It is complementary to critical path or critical chain schedule management. The Critical Path Method, abbreviated CPM, is a mathematically based algorithm for scheduling a set of project activities. ... Critical Chain Project Management (CCPM) is based on methods and algorithms developed in 1997 by Eliyahu M. Goldratt. ...


Figure 3 shows the same EV curve (green) with the actual cost data from Figure 1 (in red). It can be seen that the project was actually under budget, relative to the amount of work accomplished, since the start of the project. This is a much better conclusion than might be derived from Figure 1.


Figure 4 shows all three curves together – which is a typical EVM line chart. The best way to read these three-line charts is to identify the EV curve first, then compare it to PV (for schedule performance) and AC (for cost performance). It can be seen from this illustration that a true understanding of cost performance and schedule performance relies first on measuring technical performance objectively. This is the foundational principle of EVM.


History of EVM

See also: DoD/DSMC 1997 [2] Abba 2000 [3] Fleming 2005 [4]

The genesis of EVM was in industrial manufacturing at the turn of the 20th century, but the idea took root in the United States Department of Defense in the 1960s. The original concept was called PERT/COST, but it was considered overly burdensome (not very adaptable) by contractors who were mandated to use it, and many variations of it began to proliferate among various procurement programs. In 1967, the DoD established a criterion-based approach, using a set of 35 criteria, called the Cost/Schedule Control Systems Criteria (C/SCSC). In 1970s and early 1980s, a subculture of C/SCSC analysis grew, but the technique was often ignored or even actively resisted by project managers in both government and industry. C/SCSC was often considered a financial control tool that could be delegated to analytical specialists. Department of Defense redirects here. ... The 1960s decade refers to the years from 1960 to 1969. ... In sociology, anthropology and cultural studies, a subculture is a set of people with a set of behaviors and beliefs, culture, which could be distinct or hidden, that differentiate them from the larger culture to which they belong. ... A project manager is the person who has the overall responsibility for the successful planning and execution of any project. ...


In the late 1980s and early 1990s, EVM emerged as a project management methodology to be understood and used by managers and executives, not just EVM specialists. In 1989, EVM leadership was elevated to the Undersecretary of Defense for Acquisition, thus making EVM an essential element of program management and procurement. In 1991, Secretary of Defense Dick Cheney canceled the Navy A-12 Avenger II Program due to performance problems detected by EVM. This demonstrated conclusively that EVM mattered to secretary-level leadership. In the 1990s, many U.S. Government regulations were eliminated or streamlined. However, EVM not only survived the acquisition reform movement, but became strongly associated with the acquisition reform movement itself. Most notably, from 1995 to 1998, ownership of EVM criteria (reduced to 32) were transferred to industry by adoption of ANSI EIA 748-A standard[5]. The United States Secretary of Defense is the head of the United States Department of Defense, concerned with the armed services and The Secretary is a member of the Presidents Cabinet. ... Richard Bruce Dick Cheney (born January 30, 1941), is the 46th and current Vice President of the United States, serving under President George W. Bush. ... The A-12 Avenger II was an American aircraft program from McDonnell Douglas and General Dynamics intended to be an all-weather, stealth attack replacement for the A-6 Intruder in the United States Navy and Marines. ... The Federal Acquisition Regulations, usually referred to as the FAR (or sometimes F.A.R.), are a series of regulations issued by the U.S. Federal government that concern the requirements of contractors for selling to the government, the terms under which the government obtains ownership, title and control of...


EVM was not limited to the DoD for long. It was quickly adopted by the National Aeronautics and Space Administration, United States Department of Energy and other technology-related agencies. Many industrialized nations also began to utilize EVM in their own procurement programs. The construction industry was an early commercial adopter of EVM. Closer integration of EVM with project management profession accelerated in the 1990s. The primary professional association for EVM, called the Performance Management Association merged with the Project Management Institute (PMI) in 1999 to become PMI’s first college, the College of Performance Management. An overview of EVM was included in first PMBOK Guide® First Edition in 1987 and expanded in subsequent editions. Efforts to simplify and generalize EVM gained momentum in the early 2000s. The United States Office of Management and Budget began to mandate the use of EVM across all government agencies, and for the first time, for certain internally-managed projects (not just for contractors). EVM also received greater attention by publicly traded companies in response to the Sarbanes-Oxley Act of 2002. AACE International now offers an Earned Value Professional(EVP)certification based on the ANSI/EIA 748-A standard. NASA Logo Listen to this article · (info) This audio file was created from the revision dated 2005-09-01, and does not reflect subsequent edits to the article. ... The United States Department of Energy (DOE) is a Cabinet-level department of the United States government responsible for energy policy and nuclear safety. ... PMI logo. ... This article is being considered for deletion in accordance with Wikipedias deletion policy. ... The Office of Management and Budget (OMB) is a body within the Executive Office of the President of the United States (EOP) which is tasked with coordinating United States Federal agencies. ... The Sarbanes-Oxley Act of 2002 (107 H.R. 3763), signed into law on 30 July 2002, is considered the most significant change to federal securities laws in the United States since the New Deal. ... AACE International (the Association for the Advancement of Cost Engineering) was founded in 1956 by 59 cost estimators and cost engineers during the organizational meeting of the American Association of Cost Engineering at the University of New Hampshire in Durham, New Hampshire. ...


Scaling EVM from Simple to Advanced Implementations

The foundational principle of EVM, mentioned above, does not depend on the size or complexity of the project. However, the implementations of EVM can vary significantly depending on the circumstances. In many cases, organizations establish an all-or-nothing threshold; projects above the threshold require a full-featured (complex) EVM system and projects below the threshold are exempted. Another approach that is gaining favor is to scale EVM implementation according to the project at hand and skill level of the project team. [6] [7]


Simple Implementations (emphasizing only technical performance)

There are many more small and simple projects than there are large and complex ones, yet historically only the largest and most complex have enjoyed the benefits of EVM. Still, lightweight implementations of EVM are achievable by any person who has basic spreadsheet skills. In fact, spreadsheet implementations are an excellent way to learn basic EVM skills. Screenshot of a spreadsheet under OpenOffice A spreadsheet is a rectangular table (or grid) of information, often financial information. ...


The first step is to define the work. This is typically done in a hierarchical arrangement called a work breakdown structure (WBS) although the simplest projects may use a simple list of tasks. In either case, it is important that the WBS or list be comprehensive. It is also important that each element be mutually exclusive, so that work is easily categorized in one and only one element of work. The most detailed elements of a WBS hierarchy (or the items in a list) are called terminal elements of work. In logic, two mutually exclusive (or mutual exclusive according to some sources) propositions are propositions that logically cannot both be true. ... In project management, a terminal element is the lowest element (activity or deliverable) in a work breakdown structure(WCS); it is not further subdivided. ...


The second step is to assign a value, called planned value (PV), to each terminal element. For large projects, PV is almost always an allocation of the total project budget, and may be in units of currency (e.g. dollars or euros) or in labor hours, or both. However, in very simple projects, each terminal element may be assigned a weighted “point value" which might not be a budget number. Assigning weighted values and achieving consensus on all PV quantities yields an important benefit of EVM, because it exposes misunderstandings and miscommunications about the scope of the project, and resolving these differences should always occur as early as possible. Some terminal elements can not be known (planned) in great detail in advance, and that is expected, because they can be further refined at a later time.


The third step is to define “earning rules” for each terminal element. The simplest method is to apply just one earning rule, such as the 0/100 rule, to all terminal elements. Using the 0/100 rule, no credit is earned for an element of work until it is finished. A related rule is called the 50/50 rule, which means 50% credit is earned when an element of work is started, and the remaining 50% is earned upon completion. Other fixed earning rules such as a 25/75 rule or 20/80 rule are gaining favor, since they assign more weight to finishing work than for starting it, but they also motivate the project team to identify when an element of work is started, which can improve awareness of work-in-progress. These simple earning rules work well for small or simple projects because generally each terminal element tends to be fairly short in duration.


These initial three steps define the minimal amount of planning for simplified EVM. The final step is to execute the project according to the plan and measure forward progress. When terminal elements are started and/or finished, EV is accumulated according to the earning rule. This is typically done at regular intervals (e.g. weekly or monthly), but there is no reason why EV cannot be accumulated in near real-time, when work elements are started/completed. In fact, waiting to update EV only once per month (simply because that is when cost data are available) only detracts from a primary benefit of using EVM, which is to create a technical performance scoreboard for the project team. A scoreboard is a large board for publicly displaying the score in a game or match. ...

In a lightweight implementation such as described here, the project manager has not accumulated cost nor defined a detailed project schedule network (i.e. using a critical path or critical chain methodology). While such omissions are inappropriate for managing large projects, they are a common and reasonable occurrence in many very small or simple projects. Any project can benefit from using EV alone as a real-time score of forward progress. One useful result of this very simple approach (without schedule models and actual cost accumulation) is to compare EV curves of similar projects, as illustrated in Figure 5. In this example, the progress of three residential construction projects are compared by aligning the starting dates. If these three home construction projects were measured with the same PV valuations, the relative schedule performance of the projects can be easily compared. Image File history File links EVM_Fig5. ...

Intermediate Implementations (integrating technical and schedule performance)

In many projects, schedule performance (completing the work on time) is equal in importance to technical performance. For example, some new product development projects place a high premium on finishing quickly. It is not that cost is unimportant, but finishing after a competitor may cost a great deal more in lost market share. It is likely that these kinds of projects will not use lightweight version of EVM described in the previous section, since there is no planned timescale for measuring schedule performance. A second layer of EVM skill can be very helpful in managing the schedule performance of these “intermediate” projects. The project manager may employ a critical path or critical chain to build a project schedule model. As in the lightweight implementation, the project manager must define the work comprehensively, typically in a WBS hierarchy. He/she will construct a project schedule model that describes the precedence links between elements of work. This schedule model can then be used to develop the PV curve (or baseline), as shown in Figure 2'. In business and engineering, new product development (NPD) is the term used to describe the complete process of bringing a new product or service to market. ... The Critical Path Method, abbreviated CPM, is a mathematically based algorithm for scheduling a set of project activities. ... Critical Chain Project Management (CCPM) is based on methods and algorithms developed in 1997 by Eliyahu M. Goldratt. ... A project network is a graph (flow chart) depicting the sequence in which a projects terminal elements are to be completed by showing terminal elements and their dependencies. ...


It should be noted that measuring schedule performance using EVM does not replace the need to understand schedule performance in terms of the project's schedule model (precedence network). However, EVM schedule performance, as illustrated in Figure 2 provides an additional indicator -- one that can be communicated in a single chart. Although it is theoretically possible that detailed schedule analysis will yield different conclusions than broad schedule analysis, in practice there tends to be a high correlation between the two. Although EVM schedule measurements are not necessarily conclusive, they provide useful diagnostic information. A project network is a graph (flow chart) depicting the sequence in which a projects terminal elements are to be completed by showing terminal elements and their dependencies. ...


In intermediate and advanced EVM implementations, many more earning rules are commonly used. Earning rules in addition to the 0/100, 50/50 and 25/75 "fixed formulas" mentioned above include weighted milestones, percent complete estimates, equivalent units, earned standards, apportioned effort, and level of effort (LOE). The relative strengths and weaknesses of these rules are beyond the scope of this article. Their implementation usually requires software tools more capable than spreadsheets.


Although such intermediate implementations do not require units of currency (e.g. dollars), it is common practice to use budgeted dollars as the scale for PV and EV. It is also common practice to track labor hours in parallel with currency. In EVM implementations that do use budgets as the scale of measurement, the acronyms PV, EV may be replaced by the traditional acronyms Budgeted Cost of Work Scheduled (BCWS), Budgeted Cost for Work Performed (BCWP). Budgeted Cost of Work Scheduled (BCWS) is also referred to as Planned value (PV). ...


The following EVM formulas are for schedule management, and do not require accumulation of actual cost (AC). This is important because it is not uncommon in small and intermediate size projects for true costs to be unknown or unavailable.

Schedule Variance (SV($))
begin{matrix}SV($) & = & BCWP - BCWS   & = & EV - PV end{matrix}, greater than 0 is good (ahead of schedule)
Schedule Performance Index (SPI)
SPI = {BCWP over BCWS }, greater than 1 is good (ahead of schedule)
or
SPI = {EV over PV}
See also Earned Schedule for a description of known limitations in SV($) and SPI formulas and an emerging practice for correcting these limitation.

Earned Schedule (ES) is an extension to the theory and practice of Earned Value Management (EVM). ...

Advanced Implementations (integrating cost, technical and schedule performance)

In addition to managing technical and schedule performance, a requirement of managing large and complex projects is tracking cost performance at regular intervals. To measure cost performance, planned value (or BCWS) and earned value (or BCWP) must be in units of currency (the same units that actual costs are measured.) In large implementations, the planned value curve is commonly called a Performance Measurement Baseline (PMB) and may be arranged in control accounts, summary-level planning packages, planning packages and work packages. In large projects, establishing control accounts is the primary method of delegating responsibility and authority to various parts of the performing organization. Control accounts are cells of a responsibility assignment matrix, which is intersection of the project WBS and the organizational breakdown structure (OBS). Control accounts are assigned to Control Account Managers (CAMs). Large projects require more elaborate processes for controlling baseline revisions, more thorough integration with subcontractor EVM systems, and more elaborate management of procured materials. This article or section does not cite its references or sources. ... An organizational chart is a chart which represents the structure of an organization in terms of rank. ...


In the United States, the primary standard for full-featured EVM systems is the ANSI EIA-748A standard, published in May 1998 and reaffirmed in August 2002. The standard defines 32 criteria for full-featured EVM system compliance. As of the year 2007, a draft of EIA-748B, a revision to the original is available from ANSI. Other countries have established similar standards.


In addition to using BCWS and BCWP, full-featured (traditional) implementations often use the term Actual Cost of Work Performed (ACWP) instead of AC. Additional acronyms and formulas include:

Budget at Completion (BAC): The total planned value (PV or BCWS) at the end of the project. If a project has a Management Reserve (MR), it is typically in addition to the BAC.
Cost Variance (CV)
begin{matrix}CV & = & BCWP - ACWP   & = & EV - AC end{matrix}, greater than 0 is good (under budget)
Cost Performance Index (CPI)
CPI = {BCWP over ACWP}
< 1 means that the cost of completing the work is higher than planned (bad)
= 1 means that the cost of completing the work is right on plan (good)
> 1 means that the cost of completing the work is less than planned (good or sometimes bad).
Having a CPI that is very high (in some cases, very high is only 1.2) may mean that the plan was too conservative, and thus a very high number may in fact not be good, since the CPI is being measured against a poor baseline. Management or the customer may be upset with the planners since an overly conservative baseline ties up available funds for other purposes, and the baseline is also used for manpower planning.
Estimate At Completion (EAC)
EAC is the manager's projection of total cost of the project at completion.
 begin{align} EAC = AC + {(BAC-EV)over CPI} end{align}
ETC is the estimate to complete the project.
 begin{align} ETC = EAC - ACWP end{align}
To-Complete Performance Index (TCPI)
The TCPI projects what the CPI will be for the remainder of the project based on the manager's projection of subsequent performance. The TCPI should be compared to the CPI. Any significant difference should be accounted for to explain why the manager projects either improved or degraded performance in the future.
TCPI = { left( BAC - BCWP right) over ETC }
Independent Estimate At Completion (IEAC)
The IEAC is a metric to project total cost using the performance to date to project overall performance. This can be compared to the EAC, which is the manager's projection.
IEAC = sum ACWP + { left( BAC - sum BCWP right) over CPI }
or
IEAC = sum AC + { left(BAC -sum EV right) over CPI }

Limitations of EVM

If the implementation of EVM is not scaled to match the size and complexity of the project at hand, it may be either too lightweight (e.g. not standard-compliant) or too costly. The benefits of any implementation should far outweigh its cost of implementation and maintenance. Thus, EVM is a project management discipline that should pay for itself many times over.


EVM has no provision to measure project quality, so it is possible for EVM to indicate a project is under budget, ahead of schedule and scope fully executed, but still have unhappy clients and ultimately unsuccessful results. In other words, EVM is only one tool in the project manager's toolbox.


The use of EVM presumes that stakeholders care about measuring progress objectively. If a project team does not want to measure performance objectively, or if the organization is performing EVM just to fulfill a customer requirement, EVM is unlikely to help.


Since EVM requires quantification of a project plan, it is often perceived to be inapplicable to discovery-driven or Agile software development projects. For example, it may be impossible to plan certain research projects far in advance, since research itself uncovers some opportunities (research paths) and actively eliminates others. However, another school of thought holds that all work can be planned, even if in weekly timeboxes or other short increments. Thus, the challenge is to create agile or discovery-driven implementations of the EVM principle, and not simply to reject the notion of measuring technical performance objectively. (See the lightweight implementation for small projects, described above). Applying EVM in fast-changing work environments is, in fact, an area of project management research. Sulaiman 2007 [8] Look up agile in Wiktionary, the free dictionary. ... This article is about the concept. ... In Project management, a timebox is a period of time in which to accomplish some task. ... Iterative and Incremental development is a software development process, as opposed to more traditional waterfall model. ...


Traditional EVM is not intended for non-discrete (continuous) effort. In traditional EVM standards, non-discrete effort is called “level of effort" (LOE). If a project plan contains a significant portion of LOE, and the LOE is intermixed with discrete effort, EVM results will be contaminated. This is another area of EVM research.


Traditional definitions of EVM typically assume that project accounting and project network schedule management are prerequisites to achieving any benefit from EVM. Many small projects don't satisfy either of these prerequisites, but they too can benefit from EVM, as described for simple implementations, above. Other projects can be planned with a project network, but do not have access to true and timely actual cost data. In practice, the collection of true and timely actual cost data can be the most difficult aspect of EVM. Such projects can benefit from EVM, as described for intermediate implementations, above, and Earned Schedule. Project accounting is the practice of creating financial reports specifically designed to track the financial progress of projects, which can then be used by managers to aid project management. ... A project network is a graph (flow chart) depicting the sequence in which a projects terminal elements are to be completed by showing terminal elements and their dependencies. ... Earned Value Management (commonly abbreviated and referred to just as EVM) is a project management technique that seeks to measure forward progress in an objective manner. ... Earned Value Management (commonly abbreviated and referred to just as EVM) is a project management technique that seeks to measure forward progress in an objective manner. ... Earned Schedule (ES) is an extension to the theory and practice of Earned Value Management (EVM). ...


See also

Aggregate planning Agile software development Critical path method Critical chain Cost overrun Dependency Duration (project management) Dynamic Systems Development Method Earned Schedule Earned value management Estimation Estimation in software engineering Event chain diagram Event chain methodology Extreme project management Float (project management) Focused improvement Fordism Gantt, Henry Gantt chart Goal... Earned Schedule (ES) is an extension to the theory and practice of Earned Value Management (EVM). ...

Notes and References

  1. ^ Marshall, Robert A.. "The contribution of earned value management to project success on contracted efforts: A quantitative statistics approach within the population of experienced practitioners". Papers presented at IRNOP VII October 11-13 2006 in Xian, China: pp. 739-751. Retrieved on 2006-10-26. 
  2. ^ Defense Systems Management College (1997). Earned Value Management Textbook, Chapter 2. Defense Systems Management College, EVM Dept., 9820 Belvoir Road, Fort Belvoir, VA 22060-5565. 
  3. ^ Abba, Wayne (2000-04-01). How Earned Value Got to Prime Time: A Short Look Back and a Glance Ahead. PMI College of Performance Management (www.pmi-cpm.org). Retrieved on 2006-10-31.
  4. ^ Fleming, Quentin; Joel Koppelman (2005). Earned Value Project Management, Third Edition, Project Management Institute. ISBN 1-930699-89-1. 
  5. ^ (1998) ANSI EIA-748A Standard, June1998, Electronic Industries Alliance. 
  6. ^ Sumara, Jim; John Goodpasture (1997-9-29). Earned Value -- The Next Generation -- A Practical Application for Commercial Projects. Retrieved on 2006-10-26.
  7. ^ Goodpasture, John C. (2004). Quantitative Methods in Project Management. J. Ross Publishing, pp. 173-178. ISBN 1-932159-15-0. 
  8. ^ Sulaiman, Tamara (2007-01-08). AgileEVM -- Earned Value Management The Agile Way. Agile Journal. Retrieved on 2007-03-07.

Year 2006 (MMVI) was a common year starting on Sunday of the Gregorian calendar. ... is the 299th day of the year (300th in leap years) in the Gregorian calendar. ... Year 2006 (MMVI) was a common year starting on Sunday of the Gregorian calendar. ... is the 304th day of the year (305th in leap years) in the Gregorian calendar. ... Year 2006 (MMVI) was a common year starting on Sunday of the Gregorian calendar. ... is the 299th day of the year (300th in leap years) in the Gregorian calendar. ... Year 2007 (MMVII) is the current year, a common year starting on Monday of the Gregorian calendar and the AD/CE era in the 21st century. ... is the 66th day of the year (67th in leap years) in the Gregorian calendar. ...

External links

  • PMI College of Performance Management
  • US DoD Earned value management website
  • The Acquisition Community Connection on EVM
  • EVM at NASA
  • EVM in the Australian Department of Defence
  • UK MoD on-line training using Flash player
  • Online tool for creating EV charts
  • Start With "Simple" Earned Value On All Your Projects
  • AACE Internationals' Earned Value Professional Certification

  Results from FactBites:
 
Earned Value Management (270 words)
Earned Value Management is an integrated program management technique that integrates technical performance requirements, resource planning, with schedules, while taking risk into consideration.
The major objectives of applying earned value to a contract are to encourage contractors to use effective internal technical, cost and schedule management control systems, and to permit the customer to rely on timely data produced by those systems for better management insight.
There are two major objectives of an earned value system: to encourage contractors to use effective internal cost and schedule management control systems; and to permit the customer to be able to rely on timely data produced by those systems for determining product-oriented contract status.
ColabWiki: Earned Value Management (414 words)
EVM is a project (investment) management tool effectively integrating the investment scope of work with schedule and cost elements for optimum investment planning and control.
Earned Value Management is a project management technique that relates resource planning to schedules and to technical cost and schedule requirements.
An EVM is a set of business practices that, when applied to a project or program: • Integrate scope, schedule, and cost objectives, • Establish a baseline plan for accomplishment of project or program objectives, and • Employ earned value techniques for performance measurement during the execution of the project or program.
  More results at FactBites »


 
 

COMMENTARY     


Share your thoughts, questions and commentary here
Your name
Your comments

Want to know more?
Search encyclopedia, statistics and forums:

 


Lesson Plans | Student Area | Student FAQ | Reviews | Press Releases |  Feeds | Contact
The Wikipedia article included on this page is licensed under the GFDL.
Images may be subject to relevant owners' copyright.
All other elements are (c) copyright NationMaster.com 2003-5. All Rights Reserved.
Usage implies agreement with terms, 1022, m