FACTOID # 25: If you're in Montserrat, watch your back! Nearly 1% of the population are police officers.
 
 Home   Encyclopedia   Statistics   Countries A-Z   Flags   Maps   Education   Forum   FAQ   About 
 
WHAT'S NEW
RECENT ARTICLES
More Recent Articles »
 

FACTS & STATISTICS    Simple view

  1. Select countries to view: (hold down Control key and click to select several)

     

     

    Compare:

     

     

  1. Select fact or statistic: (* = graphable)

     

     

     

  2. (OPTIONAL) Compare to statistic: (both need to be graphable)

     

     

     

  3. View result as:

     

       
(OR) SEARCH ALL encyclopedia, stats & forums:   

Encyclopedia > Program Evaluation and Review Technique
PERT network chart for a seven-month project with five milestones (10 through 50) and six activities (A through F).

The Program Evaluation and Review Technique or Project Evaluation and Review Technique commonly abbreviated PERT is a model for project management invented by Booz Allen Hamilton, Inc. under contract to the United States Department of Defense's US Navy Special Projects Office in 1958 as part of the Polaris mobile submarine-launched ballistic missile project. This project was a direct response to the Sputnik crisis. Some US government contracts required that PERT be used as part of management supervision. PERT Chart. ... PERT Chart. ... Project Management is the discipline of organizing and managing resources (e. ... Booz Allen Hamilton, Inc. ... The United States Department of Defense (DOD or DoD) is the federal department charged with coordinating and supervising all agencies and functions of the government relating directly to national security and the military. ... Year 1958 (MCMLVIII) was a common year starting on Wednesday (link will display full calendar) of the Gregorian calendar. ... Polaris A-3 on launch pad in Cape Canaveral The Polaris missile was a submarine-launched, two-stage solid-fuel nuclear-armed ballistic missile (SLBM) built during the Cold War by Lockheed for the United States Navy. ... USS Virginia, a Virginia-class nuclear attack (SSN) submarine Alvin in 1978, a year after first exploring hydrothermal vents. ... Sputnik 1 The Sputnik crisis was a turn point of the Cold War that began on October 4, 1957 when the Soviet Union launched the Sputnik 1 satellite. ...


PERT is basically a method to analyze the tasks involved in completing a given project, especially the time needed to complete each task, and identifying the minimum time needed to complete the total project. A project is a temporary endeavor undertaken to create a unique product or service[1]. // The word project comes from the Latin word projectum from projicere, to throw something forwards which in turn comes from pro-, which denotes something that precedes the action of the next part of the word...


PERT was developed in the 1950’s, primarily to simplify the planning and scheduling of large and complex projects. It was able to incorporate uncertainty by making it possible to schedule a project not knowing precisely the details and durations of all the activities. It is more of an event-oriented technique rather than start- and completion-oriented, and is used more in R&D-type projects where not cost but time is a major factor.


This project model was the first of its kind, a revival for scientific management, founded in Fordism and Taylorism. Though every company now has its own "project model" of some kind, they all resemble PERT in some respect. Only DuPont corporation's critical path method was invented at roughly the same time as PERT. Taylorism or Scientific management is the name of the approach to management and Industrial/Organizational Psychology initiated by Frederick Winslow Taylor in his 1911 monograph The Principles of Scientific Management. ... Fordism is a form of production or production paradigm that prevailed in post-war decades (and perhaps even before second world war) in western industrial countries. ... Taylorism or Scientific management is the name of the approach to management and Industrial/Organizational Psychology initiated by Frederick Winslow Taylor in his 1911 monograph The Principles of Scientific Management. ... The DuPont Corporation was the Prime Contractor for the Hanford Engineering Works, a part of the Manhattan Project during World War II that was located at Hanford, Washington. ... The Critical Path Method, abbreviated CPM, is a mathematically based algorithm for scheduling a set of project activities. ...


The most famous part of PERT is the "PERT Networks", charts of timelines that interconnect. PERT is intended for very large-scale, one-time, complex, non-routine projects.

Contents

PERT terminology and conventions

Conventions

  • A PERT chart is a tool that facilitates decision making; The first draft of a PERT chart will number its events sequentially in 10s (10, 20, 30, etc.) to allow the later insertion of additional events.
  • Two consecutive events in a PERT chart are linked by activities, which are conventionally represented as arrows in the diagram above.
  • The events are presented in a logical sequence and no activity can commence until its immediately preceding event is completed.
  • The planner decides which milestones should be PERT events and also decides their “proper” sequence.
  • A PERT chart may have multiple pages with many sub-tasks.
  • PERT Charts are one of the tools used in the Earned Value Management Technique EVMT, used by many corporations today to track Earned Value.

Earned Value Management (EVM) is a project management technique that measures forward progress objectively. ...

Terminology

  • A PERT event: is a point that marks the start or completion of one or more tasks. It consumes no time, and uses no resources. It marks the completion of one or more tasks, and is not “reached” until all of the activities leading to that event have been completed.
  • A predecessor event: an event (or events) that immediately precedes some other event without any other events intervening. It may be the consequence of more than one activity.
  • A successor event: an event (or events) that immediately follows some other event without any other events intervening. It may be the consequence of more than one activity.
  • A PERT activity: is the actual performance of a task. It consumes time, it requires resources (such as labour, materials, space, machinery), and it can be understood as representing the time, effort, and resources required to move from one event to another. A PERT activity cannot be completed until the event preceding it has occurred.
  • Optimistic time (O): the minimum possible time required to accomplish a task, assuming everything proceeds better than is normally expected
  • Pessimistic time (P): the maximum possible time required to accomplish a task, assuming everything goes wrong (but excluding major catastrophes).
  • Most likely time (M): the best estimate of the time required to accomplish a task, assuming everything proceeds as normal.
  • Expected time (TE): the best estimate of the time required to accomplish a task, assuming everything proceeds as normal (the implication being that the expected time is the average time the task would require if the task were repeated on a number of occasions over an extended period of time).
TE = (O + 4M + P) ÷ 6
  • Critical Path: the longest possible continuous pathway taken from the initial event to the terminal event. It determines the total calendar time required for the project; and, therefore, any time delays along the critical path will delay the reaching of the terminal event by at least the same amount.
  • Lead time: the time by which a predecessor event must be completed in order to allow sufficient time for the activities that must elapse before a specific PERT event is reached to be completed.
  • Lag time: the earliest time by which a successor event can follow a specific PERT event.
  • Slack: the slack of an event is a measure of the excess time and resources available in achieving this event. Positive slack(+) would indicate ahead of schedule; negative slack would indicate behind schedule; and zero slack would indicate on schedule.

Implementing PERT

The first step to scheduling the project is to determine the tasks that the project requires and the order in which they must be completed. The order may be easy to record for some tasks (e.g. When building a house, the land must be graded before the foundation can be laid) while difficult for others (There are two areas that need to be graded, but there are only enough bulldozers to do one). Additionally, the time estimates usually reflect the normal, non-rushed time. Many times, the time required to execute the task can be reduced for an additional cost or a reduction in the quality. A Schedule duration crash is the effort to reduce the overall duration of a schedule. ...


In the following example there are seven tasks, labeled a through g. Some tasks can be done concurrently (a & b) while others cannot be done until their predecessor task is complete (c cannot begin until a is complete). Additionally, each task has three time estimates: the optimistic time estimate (a), the most likely or normal time estimate (m), and the pessimistic time estimate (b). The expected time (TE) is computed using the formula (a + 4m + b)/6.

Activity Predecessor Opt.
a
Norm.
m
Pess.
b
TE
(a + 4m + b)/6
a -- 2 4 6 4.00
b -- 3 5 9 5.33
c a 4 5 7 5.17
d a 4 6 10 6.33
e b, c 4 5 7 5.17
f d 3 4 8 4.50
g e 3 5 8 5.17

Note: All times listed are in work days (Mon - Fri, 8 A.M. to 5 P.M. with a one hour lunch break).


Once this step is complete, one can draw a Gantt chart or a network diagram (project management). Gantt chart showing three kinds of schedule dependencies (in red) and percent complete indications. ... PERT network chart for a seven-month project with five milestones (10 through 50) and six activities (A through F). ...

A Gantt chart created using Microsoft Project (MSP). Note (1) the critical path is in red, (2) the slack is the black lines connected to non-critical activities, (3) when using MSP, you must use the task ID when labeling predecessor activities, and (4) since Saturday and Sunday are not work days (as described above) some bars on the Gantt chart are longer if they cut through a weekend.
A Gantt chart created using OmniPlan. Note (1) the critical path is highlighted, (2) the slack is not specifically indicated on task 5 (d), though it can b observed on tasks 3 and 7 (b and f), (3) when using OmniPlan, you may use the GUI to easily link dependencies, or you may enter them by reference to task ID, and (4) since weekends are indicated by a thin vertical line, and take up no additional space on the work calendar, bars on the Gantt chart are not longer or shorter when they do or don't carry over a weekend.

A network diagram can be created by hand or by using software such as Microsoft Project. There are two types of network diagrams, activity on arrow (AOA) and activity on node (AON). Activity on node diagrams are generally easier to create and interpret. To create an AON diagram, it is recommended (but not necessary) to start with a node named start. This "activity" has a duration of zero (0). Then you draw each activity that does not have a predecessor activity (a and b in this example) and connect them with an arrow. Next, since both c and d list a as a predecessor activity, their nodes are drawn with arrows coming from a. Activity e is listed with b and c as predecessor activities, so node e is drawn with arrows coming from both b and c, signifing that e cannot begin until both b and c have been completed. Activity f has d as a predecessor activity, so an arrow is drawn connecting the activities. Likewise, and arrow is drawn from e to g. Since there are no activities that come after f or g, it is recommended (but again not necessary) to connect them to a node labeled finish. Image File history File links Pert_example_gantt_chart. ... Microsoft Project (or MSP) is a project management software program developed and sold by Microsoft which is designed to assist project managers in developing plans, assigning resources to tasks, tracking progress, managing budgets and analyzing workloads. ... The Critical Path Method, abbreviated CPM, is a mathematically based algorithm for scheduling a set of project activities. ... Float in project management is the amount of time that a terminal element in a project network can be delayed by, without causing a delay to: subsequent terminal elements (free float) project completion date (total float). ... Image File history File links No higher resolution available. ... OmniPlan is the name of The Omni Groups planning and project management software. ... The Critical Path Method, abbreviated CPM, is a mathematically based algorithm for scheduling a set of project activities. ... Float in project management is the amount of time that a terminal element in a project network can be delayed by, without causing a delay to: subsequent terminal elements (free float) project completion date (total float). ... GUI can refer to the following: GUI is short for graphical user interface, a term used to describe a type of interface in computing. ... Microsoft Project (or MSP) is a project management software program developed and sold by Microsoft which is designed to assist project managers in developing plans, assigning resources to tasks, tracking progress, managing budgets and analyzing workloads. ...

A network diagram created using Microsoft Project (MSP). Note the critical path is in red.
A node like this one (from Microsoft Visio) can be used to display the activity name, duration, ES, EF, LS, LF, and slack.

By itself, the network diagram pictured above does not give much more information than a Gantt chart; however, it can be expanded to display more information. The most common information shown is: Image File history File links Download high-resolution version (1020x591, 10 KB) Summary I created this image myself using Microsoft Project Licensing I, the creator of this work, hereby grant the permission to copy, distribute and/or modify this document under the terms of the GNU Free Documentation License, Version... Microsoft Project (or MSP) is a project management software program developed and sold by Microsoft which is designed to assist project managers in developing plans, assigning resources to tasks, tracking progress, managing budgets and analyzing workloads. ... The Critical Path Method, abbreviated CPM, is a mathematically based algorithm for scheduling a set of project activities. ... Image File history File links Pert_example_node_legend. ... Microsoft Visio is diagramming software for Microsoft Windows. ...

  1. The activity name
  2. The normal duration time
  3. The early start time (ES)
  4. The early finish time (EF)
  5. The late start time (LS)
  6. The late finish time (LF)
  7. The slack

In order to determine this information it is assumed that the activities and normal duration times are given. The first step is to determine the ES and EF. The ES is defined as the maximum EF of all predecessor activities, unless the activity in question is the first activity, which the ES is zero (0). The EF is the ES plus the task duration (EF = ES + duration). Float in project management is the amount of time that a terminal element in a project network can be delayed by, without causing a delay to: subsequent terminal elements (free float) project completion date (total float). ...

  • The ES for start is zero since it is the first activiy. Since the duration is zero, the EF is also zero. This EF is used as the ES for a and b.
  • The ES for a is zero. The duration (4 work days) is added to the ES to get an EF of four. This EF is used as the ES for c and d.
  • The ES for b is zero. The duration (5.33 work days) is added to the ES to get an EF of 5.33.
  • The ES for c is four. The duration (5.17 work days) is added to the ES to get an EF of 9.17.
  • The ES for d is four. The duration (6.33 work days) is added to the ES to get an EF of 10.33. This EF is used as the ES for f.
  • The ES for e is the greatest EF of its predecessor activities (b and c). Since b has an EF of 5.33 and c has an EF of 9.17, the ES of e is 9.17. The duration (5.17 work days) is added to the ES to get an EF of 14.34. This EF is used as the ES for g.
  • The ES for f is 10.33. The duration (4.5 work days) is added to the ES to get an EF of 14.83.
  • The ES for g is 14.34. The duration (5.17 work days) is added to the ES to get an EF of 19.51.
  • The ES for finish is the greatest EF of its predecessor activities (f and g). Since f has an EF of 14.83 and g has an EF of 19.51, the ES of finish is 19.51. Finish is a milestone (and therefore has a duration of zero), so the EF is also 19.51.

Barring any unforseen events, the project should take 19.51 work days to complete. The next step is to determine the late start (LS) and late finish (LF) of each activity. This will eventually show if there are activities that have slack. The LF is defined as the minimum LS of all successor activities, unless the activity is the last activity, for which the LF equals the EF. The LS is the LF minus the task duration (LS = LF - duration). Theory of Constraints (TOC) is an overall management philosophy that aims to continually achieve more of the goal of a system. ... Float in project management is the amount of time that a terminal element in a project network can be delayed by, without causing a delay to: subsequent terminal elements (free float) project completion date (total float). ...

  • The LF for finish is equal to the EF (19.51 work days) since it is the last activity in the project. Since the duration is zero, the LS is also 19.51 work days. This will be used as the LF for f and g.
  • The LF for g is 19.51 work days. The duration (5.17 work days) is subtracted from the LF to get a LS of 14.34 work days. This will be used as the LF for e.
  • The LF for f is 19.51 work days. The duration (4.5 work days) is subtracted from the LF to get a LS of 15.01 work days. This will be used as the LF for d.
  • The LF for e is 14.34 work days. The duration (5.17 work days) is subtracted from the LF to get a LS of 9.17 work days. This will be used as the LF for b and c.
  • The LF for d is 15.01 work days. The duration (6.33 work days) is subtracted from the LF to get a LS of 8.68 work days.
  • The LF for c is 9.17 work days. The duration (5.17 work days) is subtracted from the LF to get a LS of 4 work days.
  • The LF for b is 9.17 work days. The duration (5.33 work days) is subtracted from the LF to get a LS of 3.84 work days.
  • The LF for a is the minimum LS of its successor activities. Since c has a LS of 4 work days and d has a LS of 8.68 work days, the LF for a is 4 work days. The duration (4 work days) is subtracted from the LF to get a LS of 0 work days.
  • The LF for start is the minimum LS of its successor activities. Since a has a LS of 0 work days and b has a LS of 3.84 work days, the LS is 0 work days.

The next step is to determine the critical path and if any activities have slack. The critical path is the path that takes the longest to complete. To determine the path times, add the task durations for all available paths. Activities that have slack can be delayed without changing the overall time of the project. Slack is computed in one of two ways, slack = LF - EF or slack = LS - ES. Activities that are on the critial path have a slack of zero (0). The Critical Path Method, abbreviated CPM, is a mathematically based algorithm for scheduling a set of project activities. ... Float in project management is the amount of time that a terminal element in a project network can be delayed by, without causing a delay to: subsequent terminal elements (free float) project completion date (total float). ...

  • The duration of path adf is 14.83 work days.
  • The duration of path aceg is 19.51 work days.
  • The duration of path beg is 15.67 work days.

The critical path is aceg and the critical time is 19.51 work days. It is important to note that there can be more than one critical path (in a project more complex than this example) or the critical path can change. For example, let's say that activities d and f take their pessimistic (b) times to complete instead of their expected (TE) times. The critical path is now adf and the critical time is 22 work days. On the other hand, if activity c can be crashed to one work day, the path time for aceg is reduced to 15.34 work days, which is slightly less than the time of the new critical path, beg (15.67 work days). A Schedule duration crash is the effort to reduce the overall duration of a schedule. ...


Assuming these scenarios do not happen, the slack for each activity can now be determined.

  • Start and finish are milestones and by definition have no duration, therefore they can have no slack (0 work days).
  • The activities on the critical path by definition have a slack of zero; however, it is always a good idea to check the math anyway when drawing by hand.
    • LFa - EFa = 4 - 4 = 0
    • LFc - EFc = 9.17 - 9.17 = 0
    • LFe - EFe = 14.34 - 14.34 = 0
    • LFg - EFg = 19.51 - 19.51 = 0
  • Activity b has a LF of 9.17 and a EF of 5.33, so the slack is 3.84 work days.
  • Activity d has a LF of 15.01 and a EF of 10.33, so the slack is 4.68 work days.
  • Activity f has a LF of 19.51 and a EF of 14.83, so the slack is 3.84 work days.

Therefore, activity b can be delayed almost 4 work days without delaying the project. Likewise, activity d or activity f can be delayed 4.68 work days without delaying the project (alternatively, d and f can be delayed 2.34 work days each).

A completed network diagram created using Microsoft Visio. Note the critical path is in red.

Image File history File links Download high-resolution version (984x711, 21 KB) Summary I created this myself using Microsoft Visio Licensing I, the creator of this work, hereby grant the permission to copy, distribute and/or modify this document under the terms of the GNU Free Documentation License, Version 1. ... Microsoft Visio is diagramming software for Microsoft Windows. ... The Critical Path Method, abbreviated CPM, is a mathematically based algorithm for scheduling a set of project activities. ...

See also

Project planning is part of project management, which relates to the use of schedules such as Gantt charts to plan and subsequently report progress within the project environment. ... In probability theory and statistics, the beta distribution is a continuous probability distribution with the probability density function (pdf) defined on the interval [0, 1]: where α and β are parameters that must be greater than zero and B is the beta function. ... In probability theory and statistics, the triangular distribution is a continuous probability distribution with lower limit a, mode c and upper limit b. ... Gantt chart showing three kinds of schedule dependencies (in red) and percent complete indications. ... A project network is a graph (flow chart) depicting the sequence in which a projects terminal elements are to be completed by showing terminal elements and their dependencies. ... Project Management is the discipline of organizing and managing resources (e. ... Float in project management is the amount of time that a terminal element in a project network can be delayed by, without causing a delay to: subsequent terminal elements (free float) project completion date (total float). ... A Schedule duration crash is the effort to reduce the overall duration of a schedule. ...

External links

  • Opensource software for making AON diagram
  • The rudiments of PERT
  • More explanation of PERT
  • 3 Point Estimating Tutorial on VisionaryTools.com
  • [1]

  Results from FactBites:
 
Stanford Social Innovation Review : Articles : Luck of the Draw (March 26, 2007) (2560 words)
Program officers perform at varying levels of quality in the eyes of their grantees, and our analysis sheds light on the different categories into which they fall.
Program officers exercise a lot of personal discretion in their roles, she notes, and they work very closely with a wide variety of people.
Although program officers are the main interface between foundations and their grantees, foundation leaders often pay too little attention to assessing, developing, supporting, and clarifying the expectations of these crucial staff.
PERT Chart (1309 words)
PERT was developed in the late 1950's for the U.S. Navy's Polaris project having thousands of contractors.
PERT originally was an activity on arc network, in which the activities are represented on the lines and milestones on the nodes.
Even if the beta distribution assumption holds, PERT assumes that the probability distribution of the project completion time is the same as the that of the critical path.
  More results at FactBites »


 

COMMENTARY     


Share your thoughts, questions and commentary here
Your name
Your comments
Please enter the 5-letter protection code

Want to know more?
Search encyclopedia, statistics and forums:

 


Lesson Plans | Student Area | Student FAQ | Reviews | Press Releases |  Feeds | Contact
The Wikipedia article included on this page is licensed under the GFDL.
Images may be subject to relevant owners' copyright.
All other elements are (c) copyright NationMaster.com 2003-5. All Rights Reserved.
Usage implies agreement with terms.