Middle Eastern and North Africa Compared by Government > Red tape > Time required to get electricity > Days
DEFINITION:
Time required to get electricity (days). Time required to get electricity is the number of days to obtain a permanent electricity connection. The measure captures the median duration that the electricity utility and experts indicate is necessary in practice, rather than required by law, to complete a procedure.
CONTENTS
# | COUNTRY | AMOUNT | DATE | GRAPH | HISTORY |
---|---|---|---|---|---|
1 | Algeria | 180 | 2013 | ||
2 | Iran | 140 | 2013 | ||
3 | Israel | 132 | 2013 | ||
4 | Libya | 118 | 2013 | ||
5 | Yemen | 110 | 2013 | ||
=6 | Qatar | 90 | 2013 | ||
=6 | Bahrain | 90 | 2013 | ||
8 | Lebanon | 75 | 2013 | ||
9 | Syria | 71 | 2013 | ||
10 | Tunisia | 65 | 2013 | ||
=11 | Morocco | 62 | 2013 | ||
=11 | Oman | 62 | 2013 | ||
13 | Saudi Arabia | 61 | 2013 | ||
14 | Egypt | 54 | 2013 | ||
=15 | Iraq | 47 | 2013 | ||
=15 | Jordan | 47 | 2013 | ||
17 | Kuwait | 42 | 2013 | ||
18 | United Arab Emirates | 35 | 2013 |